Road Base and Culverts
1. There are currently 28 loads of road base in the current 2026
budget. After much discussion it was agreed that approximately
4-5 loads would be installed on Cedar Ridge at and above the
Canyon intersection, approximately 7 loads on Big Bear at the
Medano Intersection and from Victoria lane to California Circle, 1-
2 loads on Mill Run above Hampton Run, 8 Loads on Lower Mill
Run and the remaining 6 loads at the entrance gate, on the exit
road and north on Hampton Run from Lake of the Falls. At this
time no new culverts are being proposed.
2. Grading will only be done primarily on Lake of the Falls and Mill
Run and will be expanded if we receive substantial moisture. It
was also suggested to grade mill Run up to the Dan Curtis
driveway.
Road Improvements and Water Crossings
After discussion with James Cooley, our contractor, road
improvements will be completed on Cedar Ridge and Big Bear
prior to installing road base. We will continue to improve Big Bear
below Hampton Run if we receive adequate moisture. We also
discussed reducing the runoff across Mill Run near the service
road. John brought up the idea of installing a berm on the service
road above Mill Run to direct the water back to South Zapata
Creek. This was discussed with James Cooley, and he agreed with
the substantial fill that we have along Mill Run. We may also
deepen the ditch on the east side of Mill Run to prevent water
crossing the road south of the service road. We also discussed
using Len’s rock picker on a portion of Mill Run and Indian Hll.
Security Systems/Signs
Cameras have been installed and we need to purchase and install
Starlink to provide Wi-Fi service to designated computers.
Procedures need to be developed by governance for access and
monitoring of the security system data.
Purchase more gabion panels for road signs and there may be
other fencing material available for such signs.
Other Items
Finish split rail entrance fence
There was much discussion about speeding issues on the
subdivision. Speed Bumps will be installed after the Fall grading
near LOF and lower Cottonwood Loop as a test. Other areas to
consider are Lake of the Falls above Hampton Run, Hampton and
lower Mill Run . There was also discussion about renting or
borrowing a flashing sign indication speed.
Cut down and clean up dead cottonwoods by roll off and around
the exit road.
Push up wood recovery lot
2027 Budget
The 2027 budget was reviewed with 40 loads of road base and
reduced grading and rolling. The road base could be expanded in
the final budget if a breakeven net income could be achieved. As
a result, the road base budget was expanded to 50 loads.
At September 2025 meeting it was determined to put 2(Two) speed bumps on LOF not one. One at Valynn's and one above Hampton Run. 2 not 1.